Project Description

Project will improve Howe Road to a three lane road from 146th Street to 700 feet south of Cumberland Point Blvd. Includes a trail on the west side from 146th Street to the existing trail at Cumberland Point subdivision.

 
Schedule
Design is complete
Project was bid in April 2010 and completed in late Fall 2010
 
City's Project Manager
Jim Hellmann, PE
Phone: (317) 776-6330
 
Design
Butler, Fairman, & Seufert (BFS)
 
Contractor
E & B Paving, Inc.