Project Description

 
Project will improve roadway pavement and correct curves to modern roadway geometry.
 
Project start is delayed to spring 2012 due to land acquisition with the City of Indianapolis associated with the transfer of the utility assets from the City of Indianapolis to Citizens Group. Since taking over the utility, Citizens Energy has granted a right-of-entry to allow utility relocation work to begin. The water utility is an adjacent property owner.
 
Joint project between the City of Noblesville and Hamilton County.
 
Bid Opening
 
 
July 26, 2011
 
Project Start
Utility Relocation: Ongoing
Roadway: April 16, 2012
 
Closure
Closure started on April 16, 2012, and permitted to last 60 days.
Roadway opened to traffic on Friday, June 15, 2012 at approximately 2:30 PM

Project Completion
Summer 2012
 
City's Project Manager
Jim Hellmann, P.E.
Phone: (317) 776-6330
 
Design Firm
USI Consultants
 
Contractor
Berns Construction

 

 