Presley Boulevard Extension from Pleasant Street to just south of SR32

Design Engineer: Butler, Fairman, & Seufert

Contractor: Crider & Crider, Inc.

City Project Manager: Engineering Department, Jim Hellmann, jhellmann@noblesville.in.us, Ph: 317-776-6330

Project will make the following improvements:

  1. Roundabout intersection at Presley Blvd and Pleasant Street
  2. Extending the remainder of the sanitary sewer to SR32 per the sanitary sewer masterplan
  3. Box culvert of the Hare Ditch regulated drain that run between the Kahlo and Terry Lee Crossing properties

Contractor anticipates to mobilize to the site mid-July 2015, with construction being completed in Fall 2015.  

Project will require three 9AM to 3PM closures on Pleasant Street for pipe crossings. Flaggers will assist traffic during these day time closures. A traffic shift will be completed to construct the north half of the roundabout. A two-week full closure is required on Pleasant Street to construct the remainder of the roundabout. A detour route will be posted for the full closure. 

Link to project exhibit: https://www.cityofnoblesville.org/egov/documents/1435586083_79626.pdf