Midland Trail Phase 3

Project Description

As a continuation of the Midland Trail project that runs along the abandoned "Midland" central Railway corridor, this phase of the Midland Trail will run from Willowview Road to Hague Road adding approximately 4,800 feet of new trail greatly increasing the overall trail connectivity in Noblesville. 

Bid Opening

February 2019

Project Start

Sping 2019

Project Completion

August 2019

City's Project Manager

Andrew Rodewald, P.E.

Design

RQAW and A&F Engineering

Contractor

Midwest Paving, LLC.