This project is to make substantial pavement preservation improvements, from State Road 32 to Westbrook Drive. In addition, an exclusive left-turn lane will be added at the southern approach to State Road 32.  Engineering design work was completed by USI Consultants, Inc. 

 

 Highlights of the Project

·         Improvements To Existing Travel Lanes

·         Left Turn Lane At State Road 32

·         Additional Drainage Structures

Upcoming Milestones

  •  7/10/2006 - Construction contract awarded to E&B Paving, Inc.
  • Nov. 2006 - Project completed

* Schedule Is Tentative and Subject to Change.