Stony Creek Lift Station (LS2) Interceptor
PROJECT: Stony Creek Lift Station (LS2) Interceptor
TIMELINE: Tree removal in March, interceptor placement construction in late spring/early summer. The project is expected to be completed Jan. 31, 2026.
PROJECT GOALS: Adding a parallel 48-inch interceptor pipeline for the east to handle increase flow and to add bypass capability at the lift station for emergency situations.
OWNER: Noblesville Utilities
ENGINEER: American Structurepoint Inc.
CONTRACTOR: Tree removal - Martin Tree Service. Interceptor - Sub-surface of Indiana.
SCOPE: Remove only the trees needed for interceptor placement project. Place new buried interceptor and connect to Lift Station 2. Install permanent bypass capabilities at lift station.
LOCATION: Allisonville Road (0.1 miles south of Carbon Street intersection)
ESTIMATED COST: $1.8 million
COUNCIL DISTRICT: 3 (Aaron Smith)