Greenfield Avenue over Wheeler & Wheeler

 

Greenfield

PROJECT: Greenfield Avenue over Wheeler & Wheeler

TIMELINE: Roadway construction started April 1 and the road opened to traffic in early May.

    PROJECT GOALS: Replacing a culvert under Greenfield Avenue and improve the intersection of Greenfield Avenue and Arbor Grove Boulevard.

    OWNER: City of Noblesville 

    ENGINEER: WSP

    CONTRACTOR: Midwest Paving

    SCOPE: Repair culvert under Greenfield Avenue and widen intersection and improve mobility and safety at Arbor Grove subdivision entrance.

    MILEAGE: 0.25 miles

    ESTIMATED COST: $579,000

    COUNCIL DISTRICT: 5 (Dave Johnson) and 6 (Megan Wiles)