Herriman Boulevard (Phase 4)

Herriman

PROJECT: Herriman Boulevard (Phase 4)

TIMELINE: Dependent on the completion of Herriman Boulevard Phase 3 and the construction of State Road 37 and 146th Street.

PROJECT GOALS: Increased mobility and connectivity.

OWNER: City of Noblesville

ENGINEER: USI Consultants

CONTRACTOR: Not awarded 

SCOPE: Phase 4 will involve the roadway between DAG/IDI to 146th Street (pictured in red on the map above).

MILEAGE: 0.1 miles

ESTIMATED COST: $300,000

COUNCIL DISTRICT: 5 (Greg O'Connor)

Road Timeline

UPDATES

Phase 3 – Part of the SR37/146 Street Project

  • Work south of 146th Street began in September and is ongoing. Construction is expected to be mostly complete in the fall of 2020.
  • Work north of 146th Street is expected to begin after completion of the south portion.
  • Traffic restrictions on Herriman Boulevard are expected to continue until 2021.

Phase 4 – City project

  • Construction is expected to take place in 2021, dependent on SR37/146th Street construction. This could be significantly delayed if construction on the interchange is delayed.
  • The scope is Herriman Boulevard from DAG/IDI to 146th Street.

SCHEDULE EXHIBIT